Key activity summary
Key dates
Completed works
July 2023 until September 2023 |
An archaeological contractor was on site to undertake further required archaeological investigations prior to commencement of the construction groundworks programme. Groundworks are the assessment, preparation, and stabilising of ground ready for construction. |
November 2023 until March 2024
|
Localised earth works in Area 2 to provide the jack box construction platform – ground preparation. A jack box is a cement tunnel structure that will be placed under the railway tracks to minimise disruption. |
Late 2023 until March 2024 |
Tree and scrub removal, tree pollarding across the Area 1 & 2 for the SRFI Development Area. Pollarding is the pruning of trees and shrubs ensuring no long-term damage. |
Late 2023 until March 2024 |
|
Planned works
2024 |
|
January (until end of September 2025) |
Country Park Landscaping works Area 5 and Area 6 North.
PROW or Public Rights of Way are routes of land which the public can access at any time, for example, footpaths and bridleways. |
From January 2024 |
Ecology works across the site in readiness for the main earthworks contract
|
From March 2024 |
Localised works in Area 2.
A jack box is a cement tunnel structure that will be placed under the railway tracks to minimise disruption. |
March until August 2024 |
Work to Hedges Farm.
|
September 2024 until March 2025 |
British Pipeline Agency (BPA) works.
|
July 2024 (until December 2027) |
Start of main earthworks in area 1, 2 and 3. |
Home
335,000 sq m of state-of-the-art, sustainable logistics space, enveloped in 250 hectares of managed woodland and conservation grazing.
SEGRO Logistics Park RadlettMaster Plan
335,000 sq m of state-of-the-art, sustainable logistics space, enveloped in 250 hectares of managed woodland and conservation grazing.
Master plan